WELL-T Hubei Project Passes 90 Percent Process Installation Milestone

Process installation at WELL-T's Hubei project is more than 90% complete. With the main civil works finished, teams are coordinating equipment, piping, and supporting infrastructure as the project advances toward commissioning and production.

From Construction to an Integrated Production Site

The RMB 1.2 billion development occupies approximately 8.24 hectares and is a key part of WELL-T's manufacturing expansion. Production buildings, storage tanks, and pipe-rack structures are now in place.

Inside the workshops, major reactors and other equipment have been positioned. Teams are progressing equipment alignment, pipework, welding, and connections between the production areas.

Coordinated Work Across Installation Areas

Parallel work zones are helping the project maintain progress while coordinating interfaces between equipment and utilities. The reported process installation completion rate exceeds 90%, with remaining work supporting readiness for the next stage.

During the summer heat, contractors adjusted working schedules to avoid the hottest midday periods. Construction planning continues to balance progress with quality and site safety.

Expanding WELL-T's Manufacturing Foundation

The Hubei project is intended to strengthen WELL-T's production capabilities and complement its network of six production bases. The investment supports the company's long-term focus on dependable supply, product quality, and service for customers in China and overseas.